Fission Reactor Tutorial

Revision as of 02:58, 13 March 2024 by SoccPuppet (talk | contribs) (moved all the tips over here so the main page isn't as bloated)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)

Safe operations of a Fission Reactor can be difficult. Given the dangers of a meltdown, below are tutorials that may help with the maintenance.

Note that they are community-contributed, and may not be up to date.

Water based cooling

Minimal water cooled fission reactor

Water based cooling is sufficient for small setups. The actual limit is for reactors with about 75 Fission Fuel Assembly. It might be possible to go higher since larger reactors run cooler than smaller ones, but the temperature of such a reactor will be above 850K, well into the warning zone. Water cooling is ideal for players who want to start with a small-ish setup to get their feet wet with nuclear fission, or those who just don't want to bother with sodium based cooling.

Optimal turbine size vs. reactor size

A water cooled reactor has a heating rate of 20,000 mB of water for 1 mB of Fissile Fuel burnt. For your reactor to run smoothly, the turbine's max steam flow and max water output must be greater than the reactor's heating rate. The maximum steam flow can be seen on a turbine's main GUI, and the maximum water flow in the stats tab of the GUI. The Industrial Turbine's wiki page gives precise instructions on how to calculate a turbine's maximum flow based on its size and number of vents.

The math is pretty tedious, so just keep the following in mind:

  • The actual power generated per mB of Fissile Fuel depends on the number of rotor blades in the turbine. Nothing else. The actual value is 7.14 kJ per blade for 1 mB of fissile fuel. For best results, do not hesitate to build a huge turbine and power it with a tiny reactor.
  • The width of the base of the turbine only limits its rotor height (rotor height = (width * 2) - 5), not the total structure height (the Industrial Turbine's wiki page implies otherwise).
  • The limiting factor for the fissile fuel burn rate will be the minimum value between the turbine's steam flow rate (which depends on turbine size and number of turbine vents) and water flow rate (which depends on the number of condensers fitted). If need be, additional layers of condensers can be added on top of the Electromagnetic Coils layer.

Based on this, the best bang for the buck for a water cooled reactor will be a 5x9x5 turbine with a 5 blocks high rotor (10 blades), 3 coils, the rest of the coil layer fitted with 6 condensers, and a total of 33 vents. While this turbine has a max steam flow of 1,056,000 mB/t, the limiting factor here is the water flow rate: 6 condensers * 64,000 mB/t = 384,000 mB/t. The reactor's maximum burn rate will then be 384,000 / 20,000 = 19.2 mB/t which is roughly the upper limit of water cooling (running at 610 Kelvin, hot, but workable). This will generate a respectable 1.37 MJ/t of power. Also, vents may be expensive at this point for most players: 12 are enough for this setup (this will make the max steam flow rate equal to 384,000 mB/t, matching the water flow rate nicely).

Setup


The pipes and tubes connecting the reactor and turbine must have a Throughput at least equal to the heating rate of the reactor. See also #Safe operation. As mentioned above, the power drain must be higher than what the turbine actually produces (use an Induction Matrix between the turbine and the rest of the power consumers. Monitor the matrix's fill ratio regularly. To Reach a Fission reactor running at the max burnrate (1435mB) it is recommended to connect the reactor, boiler and turbine port to port to avoid issues with the Throughput.

Sample build

The picture to the right shows a minimal fission reactor setup. From left to right: Induction Matrix, Industrial Turbine, Fission Reactor. The reactor has a single Fission Fuel Assembly. It takes Fissile Fuel from its front input port, Nuclear Waste is output to the right to a Nuclear Waste Barrel. In the back behind the reactor, there are two Electric Pumps feeding the coolant loop with fresh water. The Industrial Turbine is the 5x9x5 described above. This setup generates 71.4 kJ/t when burning Fissile Fuel at its maximum of 1 mB/t. That's roughly 2.5 times less power than a Gas-Burning Generator burning Ethylene.

Sodium based cooling

Sodium cooled fission reactor
Boiler - Turbine piping

When things get too hot for your taste, Sodium is a much more efficient coolant and allows very high burn rates at lower core temperatures (but not more energy per mB of fuel burnt). Sodium based cooling requires a Thermoelectric Boiler as an intermediate heat-exchanger to cool down the Superheated sodium from the reactor and heat up water into Steam.

The Thermoelectric Boiler has been updated in Mekanism v10 to allow it to use heated coolant as a heat source. The boiler's water and steam tanks double as superheated coolant and coolant tanks. The Boiler Valves can be configured with a Configurator (crouch + right click) to make them input only, output steam or output coolant.

Optimal turbine size and boiler size vs. reactor size

With sodium cooling, the reactor will heat 200,000 of sodium per tick per mB of fissile fuel burnt. However, on the turbine's side, the steam and water flow rate requirements will be the same as in the water cooling scenario: 20,000 mB of steam/water per mB of Fissile Fuel. When sizing the turbine, just keep this in mind and use either 20,000*reactor_burn_rate or reactor_heating_rate/10.

The size of the boiler will depend on the desired tank sizes and boil rate.

Boilers have four tanks: heated coolant, water, steam and (cold) coolant. Compared to a Mekanism v9 boiler, in v10 the water tank doubles as a heated coolant tank and the steam tank doubles as a coolant tank. The water tank capacities are:

  • Water tank: external volume of the boiler from its base (included) to the topmost cavity layer, minus the number of Superheating Elements, multiplied by 16,000 mB.
  • Heated coolant tank: 16 times the size of the water tank
  • Steam tank: external volume of the boiler from the steam catch layer up to the topmost steam cavity layer multiplied by 160,000 mB. The volume includes the Pressure Dispersers, but not the topmost layer of the boiler casing.
  • Coolant tank: volume of the steam tank times 1.6

A boiler's maximum boil rate (its boil capacity) is determined by the number of installed Superheating Elements. Each element contributes 320,000 mB/t to the boiler's boil capacity. The heating layer does not have to be full of superheating elements, you can install just as many as needed such that the boiler's boil capacity greater or equal than the turbine's max steam and water flow. This will leave that much more room for the water and heated coolant.

Evaluating the boiler size is more complex. Also, to answer the question how big can make it here and now: a maximum size reactor (18x18x18) needs two boilers to run at above 800 mB/t burn rate and three steam turbines. It reaches its maximum at about 1400 mB/t where it reaches the maximum operating temperature of 1200 K.

For example with a 5x18x5 reactor (75 fuel assemblies), the boiler's heated coolant tank size must be about twice the size of the reactor's coolant tank (5*18*5 * 100,000 = 5,000,000 mB). With as much coolant buffered in the coolant return tube and as much water as the water tank's capacity buffered in the water return tubes, the reactor can be started at its maximum capacity without issues. This is a good starting point for small to mid size reactors. Again, start with low burn rates, wait the temperature and all tank levels to stabilize and increase the burn rate gradually.

Setup

Setup a Thermoelectric Boiler + Industrial Turbine as described on the boiler page with the exception that in step 7, you will need two Boiler valves on a steam catch or steam cavity layer, one for steam output, the other for coolant output.

It is important to build the boiler with water cavity layers (step 3c of the boiler's setup) in order to have a decent enough water + heated coolant storage capacity. The steam cavity layer is not really necessary here unless you have excess coolant in the system.

Next, connect the the boiler steam output (at or above the steam catch layer) to the turbine steam input, and pipe water back from one of the turbine's vents to one of the boiler's inputs at the heater or water cavity layers.

Setup some fully upgraded Electric Pumps (1 KJ/t for 1000 mB of water per tick) to inject fresh water into the water-steam loop. It is necessary to keep them running in order to keep the boiler's water tank full when running at high heating rates. How many pumps are required is left to the reader to experiment with (see #Safe operation).

For the reactor itself:

  • Connect the reactor's heated coolant output to one of the boiler's inputs at the heater or water cavity layers
  • Connect the boiler's coolant output to one of the reactor's inputs. While the boiler's valves must be placed in the proper layers. the placement of the reactor ports does not matter.
  • Connect a Fission Reactor Port configured as waste output to the top or bottom side of Nuclear Waste Barrel with a Pressurized Tube

For your reactor to run smoothly, the tubes connecting the reactor and boiler must have a Throughput greater than the heating rate of the reactor, and the tubes and pipes running between the boiler and turbine must be grater than the boiler's boil capacity (this can be seen in the boiler's stats tab).

Sample build

The picture to the right shows a 5x9x5 sodium cooled fission reactor, backed by a fairly small 5x7x5 Thermoelectric Boiler and a 7x13x7 turbine with 18 blades. It produces 3.85 MJ/t (1.54 MFE/t, 385.63 kEU/t) at peak burn rate (30 mB/t). Note that this same turbine could work with a reactor twice that size, but the boiler would need to be extended. On the right side of the reactor there is a crude, yet effective breaker-switch system (see #Safe operation).

The second picture shows the boiler and turbine piping as well as a single pump (which is not enough for this configuration).

Safe operation

The worst thing that can happen is a core meltdown, which results in explosions that occur all over the interior, and sometimes exterior of the reactor. Followed by lethal radiations over a 5 chunks radius (that's 80 blocks) that will last for several in-game weeks.

A few rules of thumb:

  • In order to avoid chunk loading related glitches, do not build a fission reactor, Thermoelectric Boiler or Industrial Turbine on a chunk boundary. If the fission reactor is partly loaded, it will continue to operate, potentially without a stable water cycle to keep it cooled.
  • Keep all chunks involved in fission power generation and waste recycling loaded (use an Anchor Upgrade in Teleporters or Quantum Entangloporters).
  • For good measure, even if a tube or pipe just crosses a chunk, keep it loaded.
  • Always start with low burn rates (the default 0.1 mB/t is good!) and increase it in small steps. Even with a positive water cycle, increases in burn rate will rapidly drain water before the cycle can catch up.
  • Use conservative on burn rates. Even the biggest reactor backed by several boilers and turbines cannot be started full blast and even less at its maximum theoretical burn rate.
  • Read the Throughput page and double check that throughput of the cables, pipes and tubes connecting the different components of your system is sufficient compared to the heating, boiling and flow rates.
  • The water flow rate of the turbine is easy to overlook. It can be checked in the turbine's stats tab and must be greater than the reactor's heating rate for water cooling and 1/10th of it for sodium cooling.


Circuit Breaker

Every reactor should have a circuit breaker that will, in many cases, prevent accidental meltdown. This can be done with redstone circuits like RS-latches or edge-detectors.

Circuit breaker

The picture to the right show a simple yet effective circuit breaker based on an edge detector.

The bottom Fission Reactor Logic Adapter is set to emit a redstone signal on high temperature. The top one is set to "activation". This will activate the reactor when it receives a redstone signal, and deactivate it whenever the signal switches off.

The piston is a regular piston with a sand or gravel block on top. The observer is facing towards the camera, sending its signal to the reactor adapter. The only issue when building this breaker it to place the observer correctly (and triple check that the adapter it will cover is set to "activation"!). The safest solution is to push it into place using a piston.

Whenever the bottom adapter will send a redstone signal, this will push the piston and gravel block, making the observer send a one redstone tick pulse to the reactor, activating it (and making it register that it is redstone activated) and deactivating it almost immediately. The redstone torch is not part of the circuit breaker itself (see below).

DISCLAIMER: A circuit breaker alone will not help in all situations. In case of reactor overheating with a large reactor and burn rate and critical coolant shortage, the temperature will have reached over 1400K before tripping the breaker. Without a quick injection of new coolant, the reactor will not cool down quickly enough and will keep taking structural damage until the unthinkable happens.

This is the purpose of the redstone torch and redstone-activated coolant tube on the right-hand side. The tube comes from a dynamic tank used as emergency coolant storage. As long as the high temperature signal is on, the tube will inject fresh coolant from the emergency tank into the reactor, bringing its temperature down much faster.

Just like for real circuit breakers a test button can be installed just beneath the observer on the face of the reactor. Pushing it should trigger the piston and activate the reactor very briefly before deactivating it.

An alarm can also be installed by using the bottom block (the one supporting the redstone dust and torch) as the input of an RS-latch and wiring the alarm on the output of the latch.

Note that this should not be used to switch off the reactor if the waste tank gets full. This is just not fast enough. A redstone comparator on a waste barrel used as buffer on the reactor's waste output is a much better solution for this purpose.

Advanced RS Latch usage

If you're producing more energy than you're utilizing, you'd be required to tune the burn rate as to never fill the internal battery of the Turbine. This can become very time consuming since you have to be constantly checking your burn rate to make sure you're never overproducing, tuning the burn rate so you're never dependent on the water coming from the Turbine, or to toggle the reactor on and off to empty the Turbine battery. If you do not do this, the Turbine will start accumulating steam, since it can no longer convert it into energy because there's nowhere to store it. If the steam storage of the Turbine gets full, it will no longer be able to repurpose the steam as water, and if your reactor depends on this to remain cool, either directly or indirectly, it will dry out fairly quickly, potentially causing a meltdown.

An easy workaround for this is to set up an Induction Matrix (a big battery) in-between your Turbine and the rest of your power network, and using redstone circuitry to store the state of the matrix (full, half full, empty, depends on your needs).

Essentially, what you need to do is set up an RS latch connecting a port from your Matrix using a comparator (arrow pointing away from the port), and the Reactor Logic Adaptor set to Activate the Reactor. The idea is, when the Matrix is full, it Sets the latch, turning the reactor off, and from here on out, all the energy that will be used comes from the battery until it's depleted. Then, once empty, it Resets the latch, turning the reactor back on, refilling the Matrix. The Matrix is still able to be drained while the latch is reset, so if it ever comes to pass that you're consuming more energy than the Reactor is producing, the circuit will never turn off.

To get the signal from an empty matrix, simply use the same comparator signal (or a different comparator from a different port on the same Matrix) and invert it, that way, when it has no charge, it can reset the latch.

There's a couple things to keep in mind with this set up:

  • You need to have ample storage of nuclear waste/spent nuclear waste, and a constant supply of Fissile Fuel, since this method allows you to set high burn rates and the reactor will remain on for long periods of time, maybe even indefinitely.
  • Make sure the Induction Provider of the Matrix has a higher input/output than the energy generated from the Turbine. If your Turbine generates more energy per tick than the Matrix can store per tick, it will accumulate on the Turbine, which is the exact scenario we're trying to avoid.
  • It's always a good idea to practice your redstone circuitry in a safe environment, away from your Reactor complex, just to be sure you understand how the latch works and what inputs and outputs you can expect from it. You can simulate a full Matrix with a redstone torch, and an empty one by the absence of a redstone torch.
  • If you already set up the circuit breaker that is explained earlier on this article, you need to use another Reactor Logic Adaptor set to Activate.
  • If you're wondering how to get the Turbine to turn excess steam back into water, you need to add a layer of Saturating Condensers inside of your Turbine, then pipe it out by connecting a Mechanical Pipe to a vent (not a valve)

Troubleshooting

Bottlenecks in the cooling chain and power drain are what limits the actual burn rate of a reactor.

The reactor must have sufficient coolant before starting it and its heated coolant tank must be empty (a non empty tank means that you have excess coolant in the system). Players who will go straight for a sodium based solution may not have yet enough sodium to fully fill the coolant tank. Even at 10% full, the reactor can still be used, just keep the burn rate low enough to always have some fresh coolant in the reactor while it is running.

Make sure that the Throughput of the pipe or tube networks for the coolant is greater than the heating rate.

Again, start with low burn rates (< 1 mB/tick) and wait for the reactor heat to stabilize. If the heat indicator turns yellow (> 600K), the reactor is running too hot (experts can push it well into the "orange zone" at 1 to 1.2K but... here be dragons). When it turns orange or red, it's time to hit the SCRAM button (and check that your circuit breaker is working). The same applies if coolant tank fills suddenly and the temperature goes up rapidly. SCRAM! Also check that the heated coolant and water levels in the boiler are stable as well as the steam level in the turbine.

When activating a reactor, some of its coolant immediately moves to the boiler as heated coolant, and some of the boiler's water moves to the turbine as steam. Having enough coolant buffered in the coolant tubes will compensate for this. As for water, you should always have several pumps ton compensate quickly. How quickly depends on how fast it drops when starting the reactor. If looking at the GUI of the boiler, the water level drops below that of the heated coolant, this is a sign that you have not enough water supply and that your boiler tank might not be large enough.

Again, an Industrial Turbine must be fitted with enough Saturating Condensers to allow a sufficient flow of water back from the turbine to the reactor or Thermoelectric Boiler. 1 mB/t of Fissile Fuel burnt requires 20000 mB/t of steam and water (this applies to water and sodium cooled reactors). Given that a condenser provides 64000 mB/t of water, this translates to 1 condenser for 3.2 mB/t of Fissile Fuel burnt.

The turbine also has an internal power storage (the gauge to the right of its GUI). When this fills up, this is a sign that there is not enough power drain in the system. If you let it reach its maximum, the turbine will stop consuming steam and sending water back into the cooling loop, resulting in a catastrophic meltdown. A solution around this is to:

  • install an induction matrix between your turbine and the rest of your base. A small matrix will do: build a 4x3x4 casing (the faces can be structural glass), install a basic provider and cell, this will give you room for two more cell and let you upgrade your cells as you get the resources to do so. The matrix GUI will give you a good view of how much power is produced and consumed at a glance.
  • Tune the reactor burn rate to be slightly above your average power usage.
  • Check the matrix from time to time. If it gets full, pop in another cell or upgrade the ones already in it. Or just deactivate the reactor and let the matrix drain.

A more expensive and extreme alternative is to enable the "dump excess" option in the turbine GUI. Like it says on the tin, this will just dump any excess steam. Doing this is dangerous unless you pump enough water into the cooling loop to compensate for the loss. For this you would need 20 (twenty) fully upgraded Electric Pumps per 1 mB/t of fissile fuel burnt.

Cookies help us deliver our services. By using our services, you agree to our use of cookies.

Need wiki hosting?

Do you need a wiki for your Minecraft mod/gaming wiki? We'll host it for free! Contact us.

Other wikis

Indie-game wikis
Powered by Indie Wikis